Tesla Giga Berlin Update – Trees Down!.

Tesla Giga Berlin planned project is absolutely moving in the planned direction. German government has just approved two most important steps needed to be taken, in order to get the construction of the fourth factory of the second most valuable car manufacturer in the world, Tesla, ready by 2021.

Giga Berlin 300 hectares – Tree Cutting Machines On Site.

Giga Berlin Steps

  1. Water supply issued has been clarified: The water association Strausberg-Erkner applied for an increase in their production capacity, so as to meet up Giga Berlin water requirement, Tesla on the other hand has also promised to use less water than the opposing parties were worried about. Brandenburg’s Environment Minister Axel Vogel also said The processing of the Strausberg-Erkner application to increase capacities should be completed this week. Then the approval notice will be issued. ”So, there is no need to worry about whether Tesla can be supplied with enough water,” Vogel added. 
  2. Tesla has been given the permission needed to clear the 300 hectares of land need for Giga Berlin

According to @Gf4Tesla The removal of the previously planted trees was decided by the administrative court in Frankfurt (Oder) on Friday in summary proceedings. Thus, applications by two nature conservation associations were unsuccessful.”

Workers are said to be working day and night, and like we previously predicted in one of our most recent posts, Tesla Giga Berlin can be operational before end of year.

Giga Berlin Can Be Operational Before 2021

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google photo

You are commenting using your Google account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: